# Throughput

also: Delivery rate

- Framework: [Kanban](https://pmdecoder.com/en/framework/kanban/)
- Reference: Kanban Guide 2025.5, Abschnitt Flow Metrics
- Edition: The Kanban Guide, May 2025
- Canonical version: https://pmdecoder.com/en/glossary/throughput/

## Definition

Throughput is one of the four flow metrics of the Kanban Guide. It indicates how many work items were completed in a unit of time, for example per day, week or month. The exact number of items is counted, without weighting by size or effort. What counts as completed is determined by the end point in the Definition of Workflow. Forecasts can be derived from the history of throughput, for example how many items are likely to be finished by a given date, often using simulations based on past values. If throughput fluctuates strongly, this points to problems in the workflow, such as large differences between items or frequent blockers.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Flow metrics](https://pmdecoder.com/en/glossary/flow-metrics/)

## Distinction

The velocity of many Scrum Teams adds up estimated story points, whereas throughput counts finished items. In the theory of constraints, throughput denotes the rate at which a system generates money through sales; the Kanban term is narrower. The number of items in progress at the same time is measured by the Work in Progress metric.

## In practice

A team processing applications for parental allowance (Elterngeld) has decided between 55 and 80 applications per week over the past twelve weeks. When the head of the authority asks whether a backlog of 400 applications can be cleared by the end of the month, the team lead uses the previous weekly figures to calculate several possible outcomes. In most of them, the time is not enough; she proposes requesting support from another unit for two weeks.

## Frequently asked questions

### Why are items not weighted by size?

The Kanban Guide requires the exact number. In practice, differences in size often even out over many items, and counting saves the effort of estimating.

### Which time period is suitable?

One that matches the rhythm of the work. Teams with many small items often measure daily or weekly, teams with few large items rather monthly.

## Related terms

- [Work item](https://pmdecoder.com/en/glossary/work-item/)
- [Story point](https://pmdecoder.com/en/glossary/story-point/)
- [Monte Carlo simulation](https://pmdecoder.com/en/glossary/monte-carlo-simulation/)
- [Theory of Constraints](https://pmdecoder.com/en/glossary/theory-of-constraints/)

---