# Three-point estimating

also: Three-point estimate

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Estimating with several values per quantity](https://pmdecoder.com/en/concept/estimating-with-several-values-per-quantity/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/three-point-estimating/

## Definition

In three-point estimating, experts do not give a single value but three: the best conceivable case, the most likely case and the unfavourable case. An expected value is calculated from these, either as a simple average or, as in PERT, as the sum of the optimistic value, four times the most likely value and the pessimistic value, divided by six. The spread between the extreme values makes the uncertainty visible.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Multipoint estimating](https://pmdecoder.com/en/glossary/multipoint-estimating/) | equivalent | — |

## Other terms

- Three-point estimate (synonym)
- PERT estimate (related, not equivalent)

## Classification

- Broader term: [Effort estimation](https://pmdecoder.com/en/glossary/effort-estimation/)

## Distinction

A single-point estimate provides only one value and conceals the uncertainty. Monte Carlo simulation uses three-point estimates for many activities as inputs and calculates probabilities for the project as a whole from them. Three-point estimating is not a separate source of information but a way of collecting values, and it can be combined with analogous or bottom-up estimates.

## In practice

For the migration of a customer database, the database expert estimates eight days in the best case, twelve days as most likely and 28 days in the worst case, if many records have to be cleaned up by hand. The weighted formula gives an expected value of 14 days. The project manager plans 14 days and records the wide range as a risk. A sample of the data in the first week is to show which scenario is more likely.

## Frequently asked questions

### Which formula is the right one?

Both are in common use. The weighted formula emphasizes the most likely value; the simple average gives the extreme values more weight. What matters is that the project calculates consistently.

### How is the pessimistic value determined?

By asking what can realistically go wrong without factoring in disasters, for example typical disruptions, queries or rework.

## Related terms

- [Activity duration](https://pmdecoder.com/en/glossary/activity-duration/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)
- [Delphi technique](https://pmdecoder.com/en/glossary/delphi-technique/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.