# Threat

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.90
- Edition: ISO 21506:2024
- Concept: [Risk with a negative effect on project objectives](https://pmdecoder.com/en/concept/risk-with-a-negative-effect-on-project-objectives/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/threat/

## Definition

A threat is the negative side of uncertainty and what people usually mean by risk in everyday language. Examples include late deliveries, the loss of key people, cost increases, technical failures or regulatory requirements. Threats are identified, assessed by probability and impact, and treated through avoidance, transfer, mitigation or acceptance.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Threat](https://pmdecoder.com/en/glossary/threat-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The opportunity is the positive counterpart. An issue is a threat that has already occurred. In information security, a threat is a possible source of harm, such as an attacker, which only becomes a risk in combination with a vulnerability; in project management the term is usually used more broadly.

## In practice

In a project to introduce a new merchandise management system, the team names as its biggest threat the possibility that the only employee who knows the legacy system might leave the company. Without him, data migration would hardly be possible. As a response, his knowledge is documented in workshops and a second person is trained. Three months later he does resign, but the migration still succeeds.

## Frequently asked questions

### Are threat and risk the same thing?

In everyday language, usually yes. In ISO 21506 and many other standards, risk is the umbrella term that covers both threats and opportunities.

### How many threats should be dealt with?

All identified threats belong in the register; the ones rated highest are actively worked on.

## Related terms

- [Opportunity](https://pmdecoder.com/en/glossary/opportunity/)
- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.