# Threat

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Risk with a negative effect on project objectives](https://pmdecoder.com/en/concept/risk-with-a-negative-effect-on-project-objectives/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/threat-pmi/

## Definition

In PMI terms, a threat is a risk with an adverse effect: if the uncertain event occurs, it would impair at least one project objective, such as schedule, cost, scope or quality. Together with opportunity, threat forms one of the two sides of the concept of risk. PMI provides specific response strategies for threats: escalate, avoid, transfer, mitigate and accept. Like any risk, a threat is assessed by probability and impact and recorded in the risk register.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Threat](https://pmdecoder.com/en/glossary/threat/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)

## Distinction

The term corresponds to threat in ISO 21506. It is narrower than risk, which in PMI terms also includes opportunities. In everyday language the same thing is often simply called “risk”, so readers of PMI texts should check whether “risk” is meant in the broad sense or only as a threat. A threat that has materialized is an issue.

## In practice

For a trade fair appearance, the team records the threat that the exhibition stand will not arrive on time because of a strike in the haulage sector. The consequence would be an empty stand on opening day. The team chooses to mitigate: the stand is shipped a week earlier and stored at the venue.

## Frequently asked questions

### Is every risk a threat in PMI terms?

No. A risk can also be an opportunity, that is an uncertainty with a positive effect. Threat refers only to the adverse side.

### What responses are there to a threat?

PMI names escalate, avoid, transfer, mitigate and accept. Which strategy fits depends on the assessment, the cost and who has authority.

## Related terms

- [Threat](https://pmdecoder.com/en/glossary/threat/)
- [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/)
- [Risk avoidance](https://pmdecoder.com/en/glossary/risk-avoidance-pmi/)
- [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation-pmi/)
- [Risk transference](https://pmdecoder.com/en/glossary/risk-transference/)

---