# Team Plan

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Pläne
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/team-plan/

## Definition

In PRINCE2, the team plan is the lowest planning level. It is produced by the team manager to plan the work on accepted work packages: which activities are needed, who carries them out, when the products will be finished and what effort is involved. Whether team plans are used and in what form depends on the project; they are not mandatory. If an external supplier works according to its own procedures, its team plan may be in its own format. In agile environments, a team’s planning, for example in iterations and backlogs, can take on the role of the team plan.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The stage plan belongs to the project manager and covers a whole stage; the team plan belongs to the team manager and relates to the work of that team. The work package defines what is to be delivered; the team plan describes how the team organizes delivery. It partly overlaps with a schedule in the general sense.

## In practice

As part of a relaunch project, an agency takes on the work package “Visual style and photo production”. In her team plan, the team manager schedules four shooting days, image selection with the client and post-production, assigns the tasks to three people and sets internal checkpoints. The project manager receives only the handover dates and the weekly updates.

## Frequently asked questions

### Does the project manager have to approve the team plan?

Not necessarily. What matters is that the team manager and the project manager agree that the work package can be delivered with the plan within the agreed tolerances.

### When is a team plan produced?

When the team manager accepts a work package, often earlier, so that the team’s estimates can feed into the stage plan.

## Related terms

- [Work Package](https://pmdecoder.com/en/glossary/work-package-prince2/)
- [Stage Plan](https://pmdecoder.com/en/glossary/stage-plan/)
- [Plans practice](https://pmdecoder.com/en/glossary/plans-practice/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Project Work Plan](https://pmdecoder.com/en/glossary/project-work-plan/)
- [Team Manager](https://pmdecoder.com/en/glossary/team-manager/)
- [Managing product delivery](https://pmdecoder.com/en/glossary/managing-product-delivery/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.