# Takt time

- Framework: [Lean](https://pmdecoder.com/en/framework/lean/)
- Canonical version: https://pmdecoder.com/en/glossary/takt-time/

## Definition

Takt time derives the pace of work from demand, not from the capacity of a machine. If 450 minutes of working time are available in a day and customers order 90 units, the takt time is five minutes: one unit must be completed every five minutes. Work steps are designed and distributed so that each step stays within this takt. If demand changes, the takt time is recalculated. In construction, the idea is transferred to areas as takt planning: a building is divided into sections of equal size, which the trades pass through one after another in fixed time windows.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Cycle time in the production sense measures how long a step actually takes for one unit; it should not exceed the takt time. Lead time measures the duration from the start to the end of the whole process. Cycle time in Kanban corresponds more closely to this lead time of a work item than to takt time. Throughput describes how much is actually completed, takt time how much ought to be completed.

## In practice

When refurbishing 120 identical bathrooms in a housing block, the main contractor divides the work into six trades and sets a takt of three working days per bathroom. Each trade has three days for one bathroom and then moves on to the next. Where a trade needs longer, the work is redistributed or a second crew is deployed until everyone keeps to the takt.

## Frequently asked questions

### Is a shorter takt time better?

Not in itself. Takt time follows from demand. Producing faster than the takt creates overproduction; producing more slowly means demand cannot be met.

### Is there a takt time outside manufacturing?

Yes, wherever similar units are produced repeatedly, for example in serial construction, in case processing or with regularly delivered software releases.

## Related terms

- [Standardized work](https://pmdecoder.com/en/glossary/standardized-work/)
- [Production levelling](https://pmdecoder.com/en/glossary/production-levelling/)
- [Just-in-time](https://pmdecoder.com/en/glossary/just-in-time/)
- [Last Planner System](https://pmdecoder.com/en/glossary/last-planner-system/)
- [Throughput](https://pmdecoder.com/en/glossary/throughput/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.