# Summary activity

also: Summary task

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Rollup of several activities in the schedule](https://pmdecoder.com/en/concept/rollup-of-several-activities-in-the-schedule/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/summary-activity/

## Definition

A summary activity structures a schedule hierarchically. It has no work of its own but is derived from the activities below it: its start is the earliest start, its finish the latest finish, and effort and costs are added up. In planning tools, summary activities can be expanded and collapsed, so that the same plan can be read in a coarse and a detailed view.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Summary activity](https://pmdecoder.com/en/glossary/summary-activity-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A normal activity describes a specific task, a summary activity a group of them. A work package in the work breakdown structure may correspond to a summary activity, but does not have to. A hammock activity, by contrast, spans the period between two independent activities without structuring them, and is used, for example, for site management or equipment hire.

## In practice

In the schedule for introducing a merchandise management system, each project phase forms a summary activity, with the teams' activities below it. Senior management sees only seven rows in its view. When a test activity takes two weeks longer, the summary activity “Test” is extended automatically, and in the collapsed plan the delay is visible immediately, without anyone having to open the details.

## Frequently asked questions

### Should dependencies be set on summary activities?

Preferably not. Links between specific activities are more precise and avoid calculation results that are hard to trace.

### Can summary activities be nested?

Yes, on any number of levels. For readability, three to four levels are usually enough.

## Related terms

- [Activity](https://pmdecoder.com/en/glossary/activity/)
- [Gantt chart](https://pmdecoder.com/en/glossary/gantt-chart/)