# Successor activity

also: Follow-on activity

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Activity that depends on another](https://pmdecoder.com/en/concept/activity-that-depends-on-another/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/successor-activity/

## Definition

A successor activity is an activity whose start or finish is tied to a preceding activity. If the predecessor is delayed, the successor moves as well, unless float absorbs the delay. An activity can have several successors; its delay then affects all of them. Only the end activity of a network schedule has no successor.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Successor activity](https://pmdecoder.com/en/glossary/successor-activity-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Successor and predecessor are the two roles in a logical relationship. The backward pass starts from the successors and determines how late an activity may finish. Later work such as maintenance is only a successor if it is actually linked in the plan.

## In practice

In planning an exhibition stand, the activity "Print stand graphics" has four successors: transport, assembly, lighting set-up and photos for the press kit. When the printer delivers two days late, the project manager checks the successors. Transport and assembly have no room to manoeuvre, whereas lighting and photos do. She arranges express transport instead of postponing all four activities.

## Frequently asked questions

### Why is it important to know the successors?

Because they show who is affected by a delay. Anyone who knows their successors can inform those affected early.

### Is all later work a successor?

No. One only speaks of a successor if a dependency has been set in the schedule.

## Related terms

- [Predecessor activity](https://pmdecoder.com/en/glossary/predecessor-activity/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass/)

---