# Successor activity

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Activity that depends on another](https://pmdecoder.com/en/concept/activity-that-depends-on-another/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/successor-activity-pmi/

## Definition

PMI uses the term successor activity for an activity that follows another activity in the logical sequence of the schedule and depends on it. The preceding activity is the predecessor activity. The type of dependency is set by the logical relationship: the most common is finish-to-start, where the successor cannot begin until the predecessor has finished. The precedence diagramming method also provides start-to-start, finish-to-finish and start-to-finish relationships. Leads and lags can add an overlap or a waiting time between the two activities. An activity can have several successors and at the same time be the successor of several other activities. These links form the network on which the forward and backward pass, float and the critical path are based.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Successor activity](https://pmdecoder.com/en/glossary/successor-activity/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)

## Distinction

In substance the successor activity matches the cross-framework term successor; the PMI name simply stresses that it is an activity in the sense of the PMI schedule. It differs from the predecessor activity only in the direction from which the same relationship is viewed. It does not refer to a succession in content, such as a follow-on project or a later product release.

## In practice

In the schedule for introducing new accounting software, the activity “Migrate master data” has two successors: “Perform test postings” is linked finish-to-start, and “Prepare user training” is linked start-to-start with a five-day lag. When the migration slips by a week, the scheduling tool immediately shows that both successors move. The project manager then checks whether preparing the training really depends on the migration and relaxes the link, because the materials can be produced with test data.

## Frequently asked questions

### Can an activity have several successor activities?

Yes. An activity can have any number of successors, for example when several development tasks start in parallel after an architecture design. Conversely, a successor can depend on several predecessors and then starts only when all conditions are met.

### Does every activity need a successor?

In a properly built network, every activity except the finish milestone has at least one successor. Activities without a successor are open ends: their delay does not mathematically affect the project finish, and float is calculated incorrectly as a result.

## Related terms

- [Successor activity](https://pmdecoder.com/en/glossary/successor-activity/)
- [Predecessor activity](https://pmdecoder.com/en/glossary/predecessor-activity-pmi/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/)