# Story point

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Relative size unit for agile work items](https://pmdecoder.com/en/concept/relative-size-unit-for-agile-work-items/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/story-point/

## Definition

Story points express how large an item is in relation to others. The team compares effort, complexity and uncertainty and assigns a point value, usually from a series based on the Fibonacci sequence such as 1, 2, 3, 5, 8 and 13. An item with eight points is considered roughly four times as large as one with two. The values cannot be converted into hours and are only comparable within a team, because each team develops its own scale. From the total of points completed in previous iterations, the velocity, teams derive how much they are likely to achieve in future.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Story point](https://pmdecoder.com/en/glossary/story-point-pmi/) | equivalent | — |

## Distinction

An effort estimate in person-days or hours is absolute and can be converted directly into costs; story points are relative. This makes quick estimates easier but comparisons between teams harder. Story points are not part of the Scrum Guide, which leaves open how sizes are determined. Other options include T-shirt sizes or simply counting items.

## In practice

A team developing a booking system for sports classes chooses a simple item as its reference, changing the profile address, and gives it two points. Connecting a payment service is given 13 points in Planning Poker, because it is unclear how well its interface is documented. Over the last four Sprints, the team has completed an average of 30 points and therefore plans no more than this amount.

## Frequently asked questions

### Why do teams estimate in points rather than hours?

Relative sizes can usually be judged more reliably than absolute durations. Points also direct attention to the task rather than to who completes it and how quickly.

### Are story points suitable for assessing performance?

This is generally advised against. Because each team has its own scale, point totals say nothing about productivity, and pressure on the figures quickly leads to inflated estimates.

## Related terms

- [Planning Poker](https://pmdecoder.com/en/glossary/planning-poker/)
- [Effort estimation](https://pmdecoder.com/en/glossary/effort-estimation/)
- [User story](https://pmdecoder.com/en/glossary/user-story/)
- [Product Backlog item](https://pmdecoder.com/en/glossary/product-backlog-item/)

---