# Steering Layer

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 4.2
- Edition: PM² Guide 3.1
- Canonical version: https://pmdecoder.com/en/glossary/steering-layer/

## Definition

The Steering Layer gives a PM² project its overall direction and makes sure that it remains aligned with its objectives. It is accountable to the Appropriate Governance Body. In terms of membership, it is made up of the roles of the Directing and Managing Layers, supplemented by optional roles such as the User Representatives or project quality assurance. In practice, the Steering Layer is therefore the Project Steering Committee. It comes to the fore above all at Phase Gates and in escalations, when decisions are taken about the project's further course.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

In German the names are easily confused: the Steering Layer is called Lenkungsebene, while the Directing Layer with the Project Owner and the Solution Provider is called Steuerungsebene. The Steering Layer is thus the committee, and the Directing Layer consists of the permanently responsible leadership roles that sit on this committee.

## In practice

In a project to introduce a learning platform, the Project Owner, the Solution Provider, the Business Manager and the Project Manager, together with a teacher as User Representative, form the Steering Layer. It meets at every Phase Gate and as needed, for example when data protection requirements call for the video function to be reassessed.

## Frequently asked questions

### Is the Steering Layer the same as the Project Steering Committee?

In practice, yes: the layer describes the function within the project organization, and the committee is the body that exercises it.

### To whom does the Steering Layer report?

To the Appropriate Governance Body on the Business Governing Layer, in particular when a project deviates significantly from its approved framework.

## Related terms

- [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/)
- [Business Governing Layer](https://pmdecoder.com/en/glossary/business-governing-layer/)
- [Directing Layer](https://pmdecoder.com/en/glossary/directing-layer/)

---