# Steering committee

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Steering body of a project](https://pmdecoder.com/en/concept/steering-body-of-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Canonical version: https://pmdecoder.com/en/glossary/steering-committee-pmi/

## Definition

A steering committee is a body of executives and key stakeholders that gives direction and support to a project, program or portfolio. It takes decisions beyond the project manager's authority, for example on approving phases, major changes or whether to continue the undertaking, and resolves conflicts between the areas involved. In PMI usage it is an element of governance; its membership, authority and meeting frequency are defined for each undertaking, often with the sponsor as chair.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/) | equivalent | — |
| PRINCE2 | [Project Board](https://pmdecoder.com/en/glossary/project-board/) | closely related | Composed of Executive, Senior User and Senior Supplier; the Executive has the final say. |
| PM² | [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/) | closely related | fixed membership chaired by the Project Owner, with the Solution Provider and other roles |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The steering committee corresponds to the steering committee in general usage. The project steering committee in PM² has a prescribed membership, whereas PMI's steering committee is tailored to each undertaking. It differs from the change control board in scope: the change control board decides on change requests, the steering committee on the direction of the whole undertaking.

## In practice

When merging two data centres, a group sets up a steering committee made up of the IT board member as sponsor, the heads of both sites, the head of procurement and a works council representative. It meets every six weeks, approves each migration wave and, when the hardware delivery is delayed, decides to change the order of the waves. The project manager prepares the meetings and submits decision papers.

## Frequently asked questions

### How large should a steering committee be?

As small as possible and as large as necessary. The areas that contribute resources or are strongly affected should be represented; more than about eight people make quick decisions difficult.

### Is the project manager a member of the steering committee?

Usually the project manager attends the meetings and reports without having a vote. The committee takes the decisions and the project manager implements them.

## Related terms

- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/)
- [Sponsor](https://pmdecoder.com/en/glossary/sponsor-pmi/)
- [Project governance](https://pmdecoder.com/en/glossary/project-governance-pmi/)
- [Change control board](https://pmdecoder.com/en/glossary/change-control-board-pmi/)

---