# Status date

also: Cut-off date

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Reference date for recorded project status](https://pmdecoder.com/en/concept/reference-date-for-recorded-project-status/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/status-date/

## Definition

The status date separates past and future in the schedule. Up to this date, actual start and finish dates, effort used, actual costs and percentages complete are entered; from this date on, remaining durations and forecasts apply. In planning tools it often appears as a vertical line in the bar chart. So that reports are comparable, the same status date applies to everyone involved.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Data date](https://pmdecoder.com/en/glossary/data-date/) | equivalent | — |

## Distinction

The status date is the reference point of an evaluation; the report date is the day on which the report is prepared or distributed. The two can be a few days apart. A milestone is a planned event in the project, a status date a point of measurement. In contract law, the German term Stichtag also refers to deadlines or valuation dates, which has nothing to do with the concept of status capture.

## In practice

A construction project reports monthly to the client, with the status date always being the last Friday of the month. By the following Wednesday, all trades report their status as at that Friday, after which the project controllers update the schedule and the cost forecast. Previously, each trade reported its status as at the day of its report, and the figures never matched. With a common status date, the reports are free of contradictions for the first time.

## Frequently asked questions

### How often should a status date be set?

In line with the reporting cycle, usually weekly or monthly. It is important to agree on it firmly and not to shift it from one report to the next.

### What does the status date mean for the schedule?

Work before the status date is regarded as done or is shown with its actual status; unfinished remaining work is moved to after the status date.

## Related terms

- [Progress report](https://pmdecoder.com/en/glossary/progress-report/)
- [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/)
- [Actual date](https://pmdecoder.com/en/glossary/actual-date/)
- [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/)

---