# Starting up a project

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozesse
- Edition: PRINCE2 7
- Concept: [Opening stage of a project](https://pmdecoder.com/en/concept/opening-stage-of-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/starting-up-a-project/

## Definition

Starting up a project is the first of the seven PRINCE2 processes and takes place before the project proper begins. It is triggered by a request from the commissioning organization. It answers the question of whether the undertaking is worthwhile and viable enough to spend time and money on a careful initiation. To do so, the Executive and the project manager are appointed, lessons from earlier projects are reviewed, the project management team is designed, an initial justification is outlined, the approach is chosen and the initiation stage is planned. The process ends with a submission to the Project Board, which decides whether to authorize initiation.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PM² | [Initiating Phase](https://pmdecoder.com/en/glossary/initiating-phase/) | partially overlapping | Short pre-project check; initiation follows as a separate process. |
| Six Sigma | [Define phase](https://pmdecoder.com/en/glossary/define-phase/) | partially overlapping | Short pre-project check; initiation follows as a separate process. |
| cross-framework | [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/) | partially overlapping | Short pre-project check; initiation follows as a separate process. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

General project initiation often covers everything up to approval. PRINCE2 separates this into two steps: starting up a project is a short pre-check, whereas initiating a project is the thorough planning that already counts as the first stage of the project. The process is not the same as a feasibility study, although such a study can itself be a separate, preceding project.

## In practice

The management of a logistics company asks for an automated small-parts warehouse to be investigated. Within three weeks the head of operations is appointed Executive and an experienced project manager is named. She reviews a similar project at a sister plant, outlines benefits and costs and proposes an approach using an external main contractor. The Project Board then authorizes initiation.

## Frequently asked questions

### Is starting up a project already part of the project?

No, it comes before. Under PRINCE2 the project begins only when the Project Board decides to authorize initiation.

### How much effort should start-up take?

As little as possible. The aim is a sound decision about initiation, not full planning, which follows in the next process.

## Related terms

- [Initiating a project](https://pmdecoder.com/en/glossary/initiating-a-project/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)
- [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/)
- [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/)
- [Executive (PRINCE2)](https://pmdecoder.com/en/glossary/executive-prince2/)
- [Project Mandate](https://pmdecoder.com/en/glossary/project-mandate-prince2/)
- [Project Brief](https://pmdecoder.com/en/glossary/project-brief/)
- [Daily Log](https://pmdecoder.com/en/glossary/daily-log/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.