# Start-to-start

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Start after another activity starts](https://pmdecoder.com/en/concept/start-after-another-activity-starts/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/start-to-start/

## Definition

Start-to-start, SS for short, is one of the four logical relationships in a schedule. It states that the successor cannot start before the predecessor has started. After that, both activities may run in parallel; the relationship does not govern when they finish. It is often combined with a lag to express that the successor can only start once the predecessor has a certain head start. This makes it possible to represent sequences in which one activity follows another section by section.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Start-to-start relationship](https://pmdecoder.com/en/glossary/start-to-start-relationship/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)

## Distinction

Start-to-start corresponds to the German Anfangsfolge in network planning. Unlike finish-to-start, the activities overlap, and unlike finish-to-finish, their starts are linked. Scheduling activities that previously followed one another in parallel using start-to-start is a form of fast tracking.

## In practice

When a fibre-optic network is laid in a residential area, one crew starts with the civil works. Blowing in the cables can start as soon as the first streets are open. In the schedule, the site manager links the two activities with start-to-start and a lag of five days. She also adds a finish-to-finish relationship so that cable blowing is not reported as complete before the civil works.

## Frequently asked questions

### Why is start-to-start often used with a lag?

Without a lag, both activities could start on the same day. In practice, the successor usually needs a certain head start from the predecessor, such as the first completed section, before it can start meaningfully.

### What is the danger of start-to-start without finish-to-finish?

The successor might finish before the predecessor in the plan, even though it depends on the predecessor's work. With work that follows section by section, the finish is therefore often linked as well.

## Related terms

- [Start-to-start relationship](https://pmdecoder.com/en/glossary/start-to-start-relationship/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Finish-to-finish](https://pmdecoder.com/en/glossary/finish-to-finish/)
- [Lag](https://pmdecoder.com/en/glossary/lag-pmi/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking-pmi/)

---