# Start-to-start relationship

abbr. SS

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Start after another activity starts](https://pmdecoder.com/en/concept/start-after-another-activity-starts/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/start-to-start-relationship/

## Definition

A start-to-start relationship ties the start of a successor to the start of its predecessor. Both can therefore run at the same time, but the second may not start before the first. It is often combined with a time interval, for example when an accompanying task is to begin two days after the main work has started.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Start-to-start](https://pmdecoder.com/en/glossary/start-to-start/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)

## Distinction

In a finish-to-start relationship the predecessor must be complete; in a start-to-start relationship its start is enough. A finish-to-finish relationship, by contrast, ties the finishes together. The start-to-start relationship is particularly suited to parallel work with the same trigger and is therefore a means of compressing schedules.

## In practice

On a large construction site, the land survey begins, and two days later the soil surveyor is to start test drilling because he needs the first survey points. The planner links the two activities with a start-to-start relationship and a time interval of two days. This way the drilling does not have to wait for the end of the entire survey, which takes three weeks.

## Frequently asked questions

### How is the start-to-start relationship abbreviated?

In English as SS. In German, it is abbreviated as AF (Anfangsfolge), and in German-language scheduling software often as AA (Anfang-Anfang).

### When does a start-to-start relationship make sense?

When a piece of work can begin shortly after another has started, for example because first interim results are sufficient.

## Related terms

- [Finish-to-start relationship](https://pmdecoder.com/en/glossary/finish-to-start-relationship/)
- [Finish-to-finish relationship](https://pmdecoder.com/en/glossary/finish-to-finish-relationship/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking/)

---