# Start-to-finish

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Finish after another activity starts](https://pmdecoder.com/en/concept/finish-after-another-activity-starts/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/start-to-finish/

## Definition

Start-to-finish, SF for short, is the rarest of the four logical relationships in a schedule. It specifies that the successor cannot be completed before the predecessor has started. The start of one activity thus determines the earliest finish of the other. The relationship is typical of handovers in which an existing state may only end once the new one is under way, such as shift changes or the parallel operation of an old and a new system. It can also carry a lag or lead.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Start-to-finish relationship](https://pmdecoder.com/en/glossary/start-to-finish-relationship/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)

## Distinction

Start-to-finish corresponds to the German Sprungfolge in network planning. It is easily confused with finish-to-start, where the order is reversed: there, the predecessor must finish before the successor starts. Many sequences described as start-to-finish can also be modelled as finish-to-start by reversing the direction, which is often easier to understand.

## In practice

When an old merchandise management system is replaced, operation of the legacy system must not end before the new system has gone live. The project manager links “new system live” as predecessor with “operate legacy system” as successor using start-to-finish. If go-live is delayed, legacy operation is extended automatically, and the cost of extending the licence becomes visible.

## Frequently asked questions

### Why is start-to-finish so rare?

Because most sequences are thought of in a forward direction, and handovers can often be represented with other relationship types. The relationship also seems counterintuitive to many people at first.

### Do scheduling tools support start-to-finish?

The common tools offer all four relationship types. Because start-to-finish is rare, its use in a plan should be briefly explained so that others can follow it.

## Related terms

- [Start-to-finish relationship](https://pmdecoder.com/en/glossary/start-to-finish-relationship/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/)
- [Start-to-start](https://pmdecoder.com/en/glossary/start-to-start/)
- [Finish-to-finish](https://pmdecoder.com/en/glossary/finish-to-finish/)

---