# Start-to-finish relationship

abbr. SF

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Finish after another activity starts](https://pmdecoder.com/en/concept/finish-after-another-activity-starts/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/start-to-finish-relationship/

## Definition

A start-to-finish relationship links the start of a predecessor to the finish of a successor. The successor may therefore only be completed once the predecessor has started. This seems counter-intuitive at first, but it describes handovers well: an old system is only to be switched off once the new one has gone live.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Start-to-finish](https://pmdecoder.com/en/glossary/start-to-finish/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)

## Distinction

The start-to-finish relationship is the rarest of the four logical relationships. Many schedulers avoid it because it is hard to read, and they represent the same logic with a milestone and finish-to-start relationships. Unlike a finish-to-start relationship, it is not the start but the finish of the successor that waits for the predecessor.

## In practice

A municipal utility is moving customer billing to a new system. The activity "Operate legacy system" may only finish once "Operate new system" has started, so that there is no gap in billing. The planner uses a start-to-finish relationship for this. If the start of the new system slips by a month, operation of the legacy system is extended automatically, and the licence costs for that month appear in the plan.

## Frequently asked questions

### How is the start-to-finish relationship abbreviated?

In English as SF. In German, it is also abbreviated as SF (Sprungfolge), and in German-language scheduling software often as AE (Anfang-Ende).

### Should start-to-finish relationships be used?

Only where they clearly represent a handover. A milestone such as "New system live" with two finish-to-start relationships is often easier to understand.

## Related terms

- [Finish-to-start relationship](https://pmdecoder.com/en/glossary/finish-to-start-relationship/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone/)

---