# Sprint

- Framework: [Scrum](https://pmdecoder.com/en/framework/scrum/)
- Reference: Scrum Guide 2020, Abschnitt Der Sprint
- Edition: Scrum Guide 2020
- Concept: [Time-boxed work cycle](https://pmdecoder.com/en/concept/time-boxed-work-cycle/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/sprint/

## Definition

In Scrum, the Sprint is the recurring work cycle in which ideas are turned into usable results. Every Sprint has a fixed length of one month or less, and the next Sprint begins as soon as the previous one ends. The four other events lie entirely within it, from Sprint Planning and the Daily Scrums through to the Review and Retrospective. While the Sprint is running, the Sprint Goal is protected, quality is not lowered, and the Product Backlog continues to be refined as needed. As the team learns more, it can renegotiate the scope of work with the Product Owner. Only the Product Owner may cancel a Sprint, and only when its Sprint Goal is no longer meaningful.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Iteration](https://pmdecoder.com/en/glossary/iteration-pmi/) | closely related | one month at most, with a Sprint Goal and fixed events; contains all the work up to the Increment |
| cross-framework | [Iteration](https://pmdecoder.com/en/glossary/iteration/) | closely related | one month at most, with a Sprint Goal and fixed events; contains all the work up to the Increment |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Scrum Event](https://pmdecoder.com/en/glossary/scrum-event/)

## Distinction

A Sprint is an iteration with fixed rules: a constant length, one Sprint Goal and four events within it. A project phase, by contrast, usually has its own duration and ends with an approval. The Scrum Guide compares each Sprint to a short project; however, continuation is not decided at a gate but discussed in the Sprint Review on the basis of the result.

## In practice

A team rebuilding the online registration of an adult education centre works in two-week Sprints that always start on a Wednesday. In the third Sprint, the goal is that participants can put themselves on a waiting list for fully booked courses. When management asks for an additional discount feature in the middle of the Sprint, the Product Owner adds it to the Product Backlog rather than changing the current Sprint. It is considered in the next Sprint Planning.

## Frequently asked questions

### Why does a Sprint last one month at most?

Longer periods increase the risk that goals become outdated and deviations are noticed late. Short Sprints ensure that the result and the approach are inspected regularly.

### May a team change the Sprint length?

The Scrum Guide requires a fixed length so that a reliable rhythm develops. Teams therefore usually change the length only deliberately and rarely, for example after a Retrospective.

## Related terms

- [Sprint Goal](https://pmdecoder.com/en/glossary/sprint-goal/)
- [Iteration](https://pmdecoder.com/en/glossary/iteration/)
- [Timeboxing](https://pmdecoder.com/en/glossary/timeboxing/)
- [Project phase](https://pmdecoder.com/en/glossary/project-phase/)

## Differences from other editions

- Scrum Guide 2017: Cancelling a Sprint was described in more detail: finished items were reviewed and usually accepted by the Product Owner, while unfinished ones were estimated again and returned to the Product Backlog. Every Sprint was regarded as a project whose horizon did not exceed one month.

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.