# Sprint Review

- Framework: [Scrum](https://pmdecoder.com/en/framework/scrum/)
- Reference: Scrum Guide 2020, Abschnitt Sprint Review
- Edition: Scrum Guide 2020
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/sprint-review/

## Definition

In the Sprint Review, the Scrum Team shows the key stakeholders what has been produced in the Sprint and discusses with them how far the Product Goal has progressed. Together, the participants also consider what has changed in the environment, for example in the market, the budget or the requirements, and derive from this what makes sense next. The Product Backlog can be adapted accordingly. In the sequence of events, the Review comes second to last, directly before the Sprint Retrospective; for a one-month Sprint it lasts at most four hours. The Scrum Guide sees it as a joint working session, not a mere demonstration.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Scrum Event](https://pmdecoder.com/en/glossary/scrum-event/)

## Distinction

Acceptance formally decides whether a deliverable meets the agreed criteria. The Sprint Review, by contrast, is a conversation about value and direction. Results may be released to users before the Review; the Review is not a gate that holds up release. The subsequent Sprint Retrospective looks not at the product but at the way the team works together.

## In practice

A team that looks after the web shop of a garden centre invites the branch managers and the purchasing department to the Sprint Review. It shows the new per-branch availability display directly in the test system. A branch manager points out that many plants are only in stock at the nursery, not in the sales area. The Product Owner creates a new item for this and puts the planned voucher feature on hold.

## Frequently asked questions

### Does the Sprint Review require a presentation?

No. The Scrum Guide warns against reducing the Review to a presentation. More important are looking at the actual result and discussing how to proceed.

### Who decides on changes in the Sprint Review?

The participants discuss them together. In the end, the Product Owner decides on the order of the Product Backlog.

## Related terms

- [Increment](https://pmdecoder.com/en/glossary/increment/)
- [Product Goal](https://pmdecoder.com/en/glossary/product-goal/)
- [Sprint Retrospective](https://pmdecoder.com/en/glossary/sprint-retrospective/)
- [Formal acceptance](https://pmdecoder.com/en/glossary/formal-acceptance/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
