# Sprint Retrospective

- Framework: [Scrum](https://pmdecoder.com/en/framework/scrum/)
- Reference: Scrum Guide 2020, Abschnitt Sprint Retrospective
- Edition: Scrum Guide 2020
- Concept: [Captured lessons from projects](https://pmdecoder.com/en/concept/captured-lessons-from-projects/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/sprint-retrospective/

## Definition

The Sprint Retrospective concludes every Sprint. In it, the Scrum Team looks at its own way of working: how collaboration between people went, which processes and tools helped or hindered, and whether the Definition of Done still fits. It identifies what worked well, which difficulties arose and how it dealt with them. Assumptions that turned out to be wrong are also discussed. At the end, the team selects the changes that will have the greatest effect and implements them as soon as possible, if appropriate as an item in the next Sprint Backlog. For a one-month Sprint, the Retrospective lasts at most three hours.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned-iso/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |
| PMI / PMBOK Guide | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |
| PRINCE2 | [Learn from experience principle](https://pmdecoder.com/en/glossary/learn-from-experience-principle/) | partially overlapping | Principle of using lessons at the start, throughout and at the end, not the lessons themselves. |
| PRINCE2 | [Lessons Log](https://pmdecoder.com/en/glossary/lessons-log/) | partially overlapping | Log in which lessons are collected during the project. |
| PRINCE2 | [Lessons Report](https://pmdecoder.com/en/glossary/lessons-report/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |
| PRINCE2 | [End Project Report](https://pmdecoder.com/en/glossary/end-project-report/) | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| PM² | [Project-End Report](https://pmdecoder.com/en/glossary/project-end-report/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |

## Classification

- Broader term: [Scrum Event](https://pmdecoder.com/en/glossary/scrum-event/)

## Distinction

The Sprint Review inspects the product, the Sprint Retrospective the team's way of working. It differs from lessons learned at the end of a project in its rhythm: insights are gathered after every Sprint and put into practice immediately rather than documented for future projects. The official German translation keeps the English name; in everyday German, Sprint-Retrospektive is also common.

## In practice

After a Sprint in which two items failed shortly before the end because test data was missing, the team at a health insurance fund discusses the causes. It turns out that everyone had assumed the business department would supply the data of its own accord. The team decides to clarify the required test data in Sprint Planning in future and adds coordination with the business department as an item to the next Sprint Backlog.

## Frequently asked questions

### Why is it called Sprint Retrospective and not Sprint-Retrospektive in German?

The official German translation of the Scrum Guide keeps the fixed elements of Scrum, that is the accountabilities, events and artifacts, in English. Both names refer to the same event.

### Must every Retrospective lead to a change in the next Sprint?

The aim is to find improvements in every Sprint and to address the most effective ones promptly. However, the 2020 Scrum Guide no longer requires one of them to be included in the next Sprint Backlog.

## Related terms

- [Sprint Review](https://pmdecoder.com/en/glossary/sprint-review/)
- [Definition of Done](https://pmdecoder.com/en/glossary/definition-of-done/)
- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/)
- [PDCA cycle](https://pmdecoder.com/en/glossary/pdca-cycle/)

## Differences from other editions

- Scrum Guide 2017: The Retrospective looked at people, relationships, processes and tools and ended with a plan for improvements in the next Sprint. At least one of the most important improvements identified in it had to be added to the following Sprint Backlog.

---