# Sprint Backlog

- Framework: [Scrum](https://pmdecoder.com/en/framework/scrum/)
- Reference: Scrum Guide 2020, Abschnitt Sprint Backlog
- Edition: Scrum Guide 2020
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/sprint-backlog/

## Definition

The Sprint Backlog records what the Developers want to achieve in the current Sprint and how. It consists of three parts: the Sprint Goal as the reason for the Sprint, the Product Backlog items chosen in Sprint Planning, and an actionable plan for turning them into an Increment. The Sprint Backlog belongs to the Developers: they create it, keep it up to date and adapt it as soon as they learn something new. It should show at any time where the work stands and be detailed enough for the team to judge its progress in the Daily Scrum.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Scrum Artifact](https://pmdecoder.com/en/glossary/scrum-artifact/)

## Distinction

The Product Backlog covers all known work on the product, the Sprint Backlog only the part for one Sprint. A schedule defines activities with durations and dependencies; the Sprint Backlog, by contrast, is a living work plan that the Developers may change daily. They can renegotiate the scope of the selected items with the Product Owner, while the Sprint Goal remains unchanged.

## In practice

The Sprint Backlog of a team developing a car-sharing app hangs as a digital board in the team room. At the top is the Sprint Goal "Vehicles can be unlocked by smartphone". Below it are five items, each with several tasks in the columns to do, in progress and done. After three days it turns out that one vehicle type uses a different interface. The Developers add two tasks and, after consulting the Product Owner, move a less important item back to the Product Backlog.

## Frequently asked questions

### May the Product Owner change the Sprint Backlog?

The Sprint Backlog belongs to the Developers. The Product Owner can suggest changes, and the scope is negotiated jointly; the Developers decide how the work is done.

### How detailed must a Sprint Backlog be?

Detailed enough for the Developers to see in the Daily Scrum how far they have got. Many teams break items down into tasks of one day or less for this purpose.

## Related terms

- [Sprint Goal](https://pmdecoder.com/en/glossary/sprint-goal/)
- [Daily Scrum](https://pmdecoder.com/en/glossary/daily-scrum/)
- [Product Backlog](https://pmdecoder.com/en/glossary/product-backlog/)
- [Burn-down chart](https://pmdecoder.com/en/glossary/burn-down-chart/)

## Differences from other editions

- Scrum Guide 2017: The Sprint Backlog consisted of the chosen Product Backlog items together with the plan for how the Increment would be built and the Sprint Goal reached; the Sprint Goal itself was not part of it. It also had to contain at least one important process improvement from the preceding Retrospective.

---