# Six Sigma project charter

- Framework: [Six Sigma](https://pmdecoder.com/en/framework/six-sigma/)
- Reference: ISO 13053-1:2011
- Edition: ISO 13053-1:2011 (DMAIC methodology)
- Concept: [Formal authorization of a project](https://pmdecoder.com/en/concept/formally-authorizing-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Canonical version: https://pmdecoder.com/en/glossary/six-sigma-project-charter/

## Definition

The Six Sigma project charter records on a few pages what an improvement project is about. It describes the problem in figures without anticipating causes or solutions, and states the goal as a measurable change in the output measure compared with the baseline. It adds the expected benefit for customers and the organization, the boundaries of the process under study, the team members including champion and project lead, and the planned tollgate dates. The charter is created in the Define phase, approved by the champion and updated when new findings emerge, for example after measurement.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Project Mandate](https://pmdecoder.com/en/glossary/project-mandate-prince2/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| ISO 21506 | [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/) | closely related | Tailored to an improvement project with a measurable output, usually shorter and still updated during the first phases. |
| PMI / PMBOK Guide | [Project charter](https://pmdecoder.com/en/glossary/project-charter/) | closely related | Tailored to an improvement project with a measurable output, usually shorter and still updated during the first phases. |
| PM² | [Project Charter](https://pmdecoder.com/en/glossary/project-charter-pm2/) | closely related | forms the basis for approval together with the business case; the project manager has already been appointed |
| PRINCE2 | [Project Brief](https://pmdecoder.com/en/glossary/project-brief/) | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| cross-framework | Project outline | partially overlapping | preliminary form, usually without formal approval |
| Scrum | — | no counterpart | Scrum does not define a formal authorization of a project |
| Kanban | — | no counterpart | — |

## Distinction

The charter serves the same purpose as the ISO 21506 project mandate or the PMI project charter: it formally authorizes a project and gives it a frame. It is, however, tailored to an improvement project with a measurable output, is usually shorter and is still adjusted during the first phases. It generally does not contain detailed plans for costs, risks and communication.

## In practice

A machine builder starts a project on late deliveries. The charter states: 23 per cent of orders in the last six months were delivered after the promised date; the goal is no more than eight per cent by year end. The scope runs from order receipt to dispatch and excludes the engineering of custom designs. The charter names the champion, the Black Belt, four team members and the tollgate dates.

## Frequently asked questions

### Why does the charter not name a solution?

Because the causes have not yet been confirmed at the start. An anticipated solution would narrow the analysis and commit the team to what may be the wrong measure.

### Who writes the charter?

Usually the project lead, that is a Black Belt or Green Belt, in consultation with the champion, who approves it and thereby commits resources.

## Related terms

- [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/)
- [Project charter](https://pmdecoder.com/en/glossary/project-charter/)
- [Define phase](https://pmdecoder.com/en/glossary/define-phase/)
- [Champion](https://pmdecoder.com/en/glossary/champion/)
- [SMART criteria](https://pmdecoder.com/en/glossary/smart-criteria/)
- [Business case](https://pmdecoder.com/en/glossary/business-case/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.