# Sensitivity analysis

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/sensitivity-analysis/

## Definition

Sensitivity analysis changes one uncertain variable after another, such as material prices, the duration of a permit procedure or sales volumes, and observes the effect on cost, schedule or economic viability. This reveals which variables are particularly critical and where more accurate estimates or responses are most worthwhile. The result is often shown as a tornado diagram, with the most influential variables at the top.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Monte Carlo simulation varies all variables randomly at the same time; sensitivity analysis usually varies one after another. Scenario analysis combines several changes into coherent pictures of the future, such as a favourable and an unfavourable case. Sensitivity analysis does not assess probabilities, only the strength of relationships.

## In practice

For the economic appraisal of a solar park, a project developer changes five variables by ten per cent each. The net present value reacts most strongly to the electricity price, followed by financing costs; construction costs come only third. The team therefore concentrates on concluding a long-term power purchase agreement instead of spending more weeks optimizing the construction tender.

## Frequently asked questions

### What does a tornado diagram show?

A horizontal bar for each variable examined, whose length indicates the range of its effect. The longest bars are at the top, producing a funnel shape.

### What are the limits of sensitivity analysis?

It usually looks at variables individually and overlooks interactions, for example when rising prices and longer durations occur together.

## Related terms

- [Monte Carlo simulation](https://pmdecoder.com/en/glossary/monte-carlo-simulation/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)
- [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.