# Senior Supplier

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Organisation
- Edition: PRINCE2 7
- Concept: [Leading role of the delivering side](https://pmdecoder.com/en/concept/leading-role-of-the-delivering-side/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/senior-supplier/

## Definition

The Senior Supplier represents on the Project Board the interests of those who design, develop, procure or implement the project’s products. These may be internal specialist departments, external suppliers or both. The role is answerable for making the promised supplier resources available and for the technical soundness of the solution. It assesses whether proposals and plans are realistic from the supplier’s point of view and helps to resolve technical problems that go beyond the project manager’s authority. If there are several major suppliers, the role can be shared by several people.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PM² | [Solution Provider](https://pmdecoder.com/en/glossary/solution-provider/) | closely related | May represent several internal and external suppliers; the project manager is appointed by the Executive, not by the Senior Supplier. |

## Distinction

The solution provider in PM² holds a similar position on the provider side. A contractor in the contractual sense is a company, whereas the Senior Supplier is a role on the directing body that can also be held by an internal manager. With external suppliers, it must be clarified how the role relates to contractual obligations.

## In practice

When a new warehouse software package is introduced, the head of internal IT takes on the Senior Supplier role together with the software vendor’s account lead. Both commit the developers needed and confirm to the Project Board that the planned interface is technically feasible.

## Frequently asked questions

### Can an external supplier sit on the Project Board?

Yes, PRINCE2 provides for this. The organization should bear in mind, however, that a supplier has its own commercial interests, for example regarding claims for additional work.

### Is the Senior Supplier responsible for product quality?

The Senior Supplier is answerable for the technical integrity of the solution and for providing supplier resources. Whether the products meet users’ needs is confirmed by the Senior User.

## Related terms

- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Solution Provider](https://pmdecoder.com/en/glossary/solution-provider/)
- [Contractor](https://pmdecoder.com/en/glossary/contractor/)
- [Senior User](https://pmdecoder.com/en/glossary/senior-user/)
- [Team Manager](https://pmdecoder.com/en/glossary/team-manager/)
- [Executive (PRINCE2)](https://pmdecoder.com/en/glossary/executive-prince2/)
- [Project Assurance (PRINCE2)](https://pmdecoder.com/en/glossary/project-assurance-prince2/)
- [Commercial Management Approach](https://pmdecoder.com/en/glossary/commercial-management-approach/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.