# Secondary risk

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Risk arising from a response](https://pmdecoder.com/en/concept/risk-arising-from-a-response/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/secondary-risk-pmi/

## Definition

In PMI terms, a secondary risk is a risk that arises only because a risk response is implemented. Every action changes the project: it ties up staff, shifts dates, or brings in new partners or technologies. Uncertainties of their own can follow from this. PMI recommends asking specifically about such follow-on risks when planning responses, recording them in the risk register, and assessing and treating them like other risks. A response only makes sense if the new risks weigh less overall than the original one.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Secondary risk](https://pmdecoder.com/en/glossary/secondary-risk/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)

## Distinction

The term corresponds to the cross-framework concept of secondary risk. A residual risk is the part of the original risk that remains after the response; a secondary risk is a different, new risk. Residual risk in ISO 21506 corresponds to PMI's residual risk, not to secondary risk.

## In practice

To mitigate schedule delays caused by an unreliable supplier, a mechanical engineering project engages a second supplier. Its components come from a different plant and could have slightly different dimensions. The team records this as a secondary risk and plans an additional incoming inspection.

## Frequently asked questions

### Does every secondary risk need a response of its own?

It is assessed like any other risk. If it lies above the thresholds it needs its own response; otherwise it can be accepted and monitored.

### Why is identifying secondary risks important?

Without this view, a well-intended action can leave the project worse off overall. The assessment shows whether the response pays off on balance.

## Related terms

- [Secondary risk](https://pmdecoder.com/en/glossary/secondary-risk/)
- [Residual risk](https://pmdecoder.com/en/glossary/residual-risk-pmi/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/)
- [Residual risk](https://pmdecoder.com/en/glossary/residual-risk/)

---