# Scrum Team

- Framework: [Scrum](https://pmdecoder.com/en/framework/scrum/)
- Reference: Scrum Guide 2020, Abschnitt Scrum Team
- Edition: Scrum Guide 2020
- Concept: [Team carrying out the project work](https://pmdecoder.com/en/concept/team-carrying-out-the-project-work/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/scrum-team/

## Definition

The Scrum Team is the core unit of Scrum. It brings together three accountabilities: one Product Owner, one Scrum Master and the Developers. The team is not split into sub-teams and has no internal hierarchy; everyone works towards the same Product Goal. The team has all the skills it needs to deliver a usable result in every Sprint and decides for itself who works on what and how. The Scrum Guide recommends a size of typically no more than ten people. The team takes care of everything concerning the product, from coordination with stakeholders to operation and further development.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PM² | [Project Core Team](https://pmdecoder.com/en/glossary/project-core-team/) | partially overlapping | includes the Product Owner and Scrum Master and is oriented to a product and its Product Goal, not to a time-limited project |
| cross-framework | [Project team](https://pmdecoder.com/en/glossary/project-team/) | partially overlapping | includes the Product Owner and Scrum Master and is oriented to a product and its Product Goal, not to a time-limited project |

## Classification

- Narrower terms: [Developer](https://pmdecoder.com/en/glossary/developer/), [Product Owner](https://pmdecoder.com/en/glossary/product-owner/), [Scrum Master](https://pmdecoder.com/en/glossary/scrum-master/)

## Distinction

A traditional project team usually works under a project manager who assigns tasks and is accountable for progress. The Scrum Team has no such role: planning the work lies with the Developers, prioritization with the Product Owner, and the Scrum Master ensures effective collaboration. Earlier versions of the Scrum Guide still distinguished a separate Development Team within the Scrum Team; since 2020 there has been only one team.

## In practice

An insurer sets up a Scrum Team of eight people for its customer portal: a product manager from the business department as Product Owner, a Scrum Master and six Developers from development, design and business consulting. When the portal is extended to include claims reporting via an app, the need grows to fourteen people. Instead of enlarging the team, it splits into two Scrum Teams that continue to share one Product Backlog and the same Product Owner.

## Frequently asked questions

### How large may a Scrum Team be?

The Scrum Guide sets no fixed upper limit but generally recommends ten people or fewer. Smaller teams coordinate more easily; if a team becomes too large, it should split into several teams working on the same product.

### Are stakeholders part of the Scrum Team?

No. Stakeholders work closely with the team, for example in the Sprint Review, but are not part of it. Only the Product Owner, the Scrum Master and the Developers belong to the Scrum Team.

## Related terms

- [Self-management](https://pmdecoder.com/en/glossary/self-management/)
- [Product Goal](https://pmdecoder.com/en/glossary/product-goal/)
- [Project team](https://pmdecoder.com/en/glossary/project-team/)
- [Stakeholder](https://pmdecoder.com/en/glossary/stakeholder/)

## Differences from other editions

- Scrum Guide 2017: The Scrum Team consisted of the Product Owner, the Scrum Master and a separate Development Team. For the Development Team, the guide recommended three to nine members, not counting the Product Owner or Scrum Master unless they also took on work in the Sprint themselves.

---