# Scope creep

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Gradual uncontrolled expansion of scope](https://pmdecoder.com/en/concept/gradual-uncontrolled-expansion-of-scope/)
- Topic area: [Scope and requirements](https://pmdecoder.com/en/area/scope-and-requirements/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/scope-creep/

## Definition

Scope creep refers to the gradual growth of project scope without schedules, costs or resources being adjusted accordingly. Typical causes are unclear requirements, a missing scope statement, favours to stakeholders and the team's ambition to deliver the best possible result. Individually the additions seem harmless; taken together they jeopardize the schedule and budget.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Scope creep](https://pmdecoder.com/en/glossary/scope-creep-pmi/) | equivalent | — |

## Other terms

- Feature creep (related, not equivalent)

## Distinction

Not every change in scope is scope creep: an assessed and approved change is a normal part of change management. Gold plating means additional features that the team builds in on its own initiative even though nobody asked for them, and is a variant of scope creep. Feature creep refers to the same phenomenon in product functions.

## In practice

During the development of an intranet, new requests arrive every week: a canteen menu, room booking, a birthday calendar. The developers implement each request quickly because it seems to involve little effort. After four months the project is seven weeks behind plan and the core function, document search, is not finished. The project manager then introduces a wish list, which is prioritized and decided on once a month.

## Frequently asked questions

### How can scope creep be prevented?

Through a clear scope statement, a binding change procedure, regular prioritization and a team that passes on additional requests instead of handling them on the side.

### Does scope creep also occur in agile projects?

Yes, when new requirements are added without others being dropped in return or the time frame being adjusted.

## Related terms

- [Project scope](https://pmdecoder.com/en/glossary/project-scope/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Requirement](https://pmdecoder.com/en/glossary/requirement/)

---