# Scope creep

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Gradual uncontrolled expansion of scope](https://pmdecoder.com/en/concept/gradual-uncontrolled-expansion-of-scope/)
- Topic area: [Scope and requirements](https://pmdecoder.com/en/area/scope-and-requirements/)
- Canonical version: https://pmdecoder.com/en/glossary/scope-creep-pmi/

## Definition

PMI understands scope creep as the uncontrolled expansion of product or project scope in which schedule, cost and resources are not adjusted accordingly. What characterizes it is not the change itself but the fact that it bypasses the agreed change procedure. Many small additions, each of which seems harmless on its own, add up until the budget or deadline can no longer be met. As countermeasures PMI relies on a clear definition of scope, an approved baseline and integrated change control, in which every extension is assessed and decided on.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Scope creep](https://pmdecoder.com/en/glossary/scope-creep/) | equivalent | — |

## Distinction

The cross-framework entry on scope creep describes the same phenomenon; here the focus is on how it fits into PMI terminology. An approved change made through a change request is not scope creep, even if it extends the scope. Gold plating, meaning the team adding features nobody asked for on its own initiative, is regarded as one cause.

## In practice

During the introduction of an intranet, the HR department repeatedly asks for “just one more form”. The developers implement the requests directly because each one is small. After three months, eighteen additional forms have been built and the launch date has slipped by six weeks. The project manager then introduces a rule that every request is recorded as a change request and presented to the steering body with its effort and schedule impact.

## Frequently asked questions

### Is every expansion of scope scope creep?

No. If an extension is assessed, approved and incorporated into the baseline with adjusted dates and resources, it is a controlled change. Scope creep occurs when this step is missing.

### Can scope creep occur in agile projects?

Yes, if new requests enter a running iteration without prioritization or the scope grows without any discussion of time and budget. A well-maintained backlog makes such growth visible.

## Related terms

- [Scope creep](https://pmdecoder.com/en/glossary/scope-creep/)
- [Project scope](https://pmdecoder.com/en/glossary/project-scope-pmi/)
- [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)

---