# Schedule variance

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Difference between earned value and planned value](https://pmdecoder.com/en/concept/difference-between-earned-value-and-planned-value/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/schedule-variance-pmi/

## Definition

In PMI usage, schedule variance (SV) is an earned value indicator that shows how far the work performed differs from the work planned at a status date. It is calculated as earned value minus planned value. A negative value means that less work has been completed than planned, a positive value that the project is ahead of plan. Because both quantities are measured in budget units, schedule variance is also a monetary amount, not a unit of time. It can be determined for the whole project, individual control accounts or work packages.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term corresponds to the cross-framework term schedule variance in the sense of earned value analysis. The schedule performance index expresses the same relationship as a ratio. Cost variance compares earned value not with the plan but with actual cost. Anyone who needs the delay in days or weeks has to analyse the schedule or use methods such as earned schedule.

## In practice

In the refurbishment of an office building, planned value at the end of April is 900,000 euros and earned value 820,000 euros. The schedule variance is therefore minus 80,000 euros. A breakdown by trade shows that almost the entire variance is due to the façade work, which started two weeks late because the scaffolding permit was delayed. The other trades are on plan.

## Frequently asked questions

### Why is schedule variance expressed in euros?

Because it is calculated from budget quantities. It shows the value of work that should have been completed by the status date but is still missing. A statement in days requires the schedule.

### What does a schedule variance of zero at project end mean?

Not necessarily that the project finished on time. At the end all work has been performed, so earned value and planned value are equal even if completion came later.

## Related terms

- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance/)
- [Schedule performance index](https://pmdecoder.com/en/glossary/schedule-performance-index-pmi/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance-pmi/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)
- [Variance](https://pmdecoder.com/en/glossary/variance-pmi/)

---