# Schedule performance index

abbr. SPI

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.84
- Edition: ISO 21506:2024
- Concept: [Schedule efficiency of work performed](https://pmdecoder.com/en/concept/schedule-efficiency-of-work-performed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/schedule-performance-index/

## Definition

The schedule performance index shows how fast a project is progressing compared with the plan, calculated as earned value divided by planned value. A value of 0.9 means that only 90 per cent of the planned work had been done by the cut-off date. The index is useful for comparing projects and for identifying trends over several reporting periods. For a rough schedule forecast, the planned duration is divided by the index.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Schedule performance index](https://pmdecoder.com/en/glossary/schedule-performance-index-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The cost performance index measures cost efficiency, the schedule performance index progress. Only together do they give a full picture: a project can be on time but expensive, or cheap but slow. Because earned value always equals planned value at the end, the schedule performance index rises towards one as the project nears completion, even if it finishes late.

## In practice

In a project to digitize building records, the schedule performance index is 0.85 after two months. At the same pace, the planned duration of twelve months would stretch to a little over fourteen. When the index falls further to 0.80 over the next two months, the client approves additional scanning workstations. A month later the value rises again to 0.93.

## Frequently asked questions

### How is the schedule performance index calculated?

As earned value divided by planned value, both cumulative up to the cut-off date.

### Does the index replace schedule planning?

No. It shows overall progress but not whether critical activities are affected. The network schedule with its critical path is still needed for that.

## Related terms

- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index/)
- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis/)

---