# Schedule performance index

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Schedule efficiency of work performed](https://pmdecoder.com/en/concept/schedule-efficiency-of-work-performed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/schedule-performance-index-pmi/

## Definition

In PMI usage, the schedule performance index (SPI) is an earned value indicator. It is calculated by dividing earned value by planned value. A value of 1 means that exactly as much work has been completed as planned; below 1 the project is behind schedule, above 1 it is ahead. An SPI of 0.9 means, put simply, that only nine tenths of the planned work has been performed so far. The indicator is well suited for comparisons between projects and across several reporting periods.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Schedule performance index](https://pmdecoder.com/en/glossary/schedule-performance-index/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term is equivalent to the ISO 21506 term schedule performance index. Schedule variance expresses the same relationship as a difference in monetary units, the SPI as a ratio. The cost performance index measures cost efficiency in the same way. Unlike an analysis of the critical path, the SPI says nothing about whether the late work threatens the finish date.

## In practice

At the end of the quarter, a project introducing HR software reports a planned value of 250,000 euros and an earned value of 200,000 euros; the SPI is 0.8. The project manager then checks the schedule and finds that the delay lies in data migration, which is on the critical path. She reports the finish date as at risk and proposes an additional migration run over a weekend.

## Frequently asked questions

### Why does the SPI always approach 1 towards the end of the project?

Because at the end all work has been completed, and earned value and planned value both equal the budget, regardless of how late the project finishes. In the final third, the classic SPI therefore loses meaning.

### Is an SPI above 1 sufficient proof of schedule adherence?

Not on its own. A project can bring forward non-critical work and show a high SPI while activities on the critical path fall behind. The SPI should therefore be checked against the schedule.

## Related terms

- [Schedule performance index](https://pmdecoder.com/en/glossary/schedule-performance-index/)
- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance-pmi/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index-pmi/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/)

---