# Schedule compression

also: Schedule acceleration

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Shortening a schedule without reducing scope](https://pmdecoder.com/en/concept/shortening-a-schedule-without-reducing-scope/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/schedule-compression/

## Definition

Schedule compression is used when a project has to reach an earlier end date or make up for a delay while the scope is to remain unchanged. The two main techniques are crashing, in which additional resources shorten the duration of critical activities, and fast tracking, in which activities that would normally follow one another run fully or partly in parallel. Both target the activities that determine the end date, because only there does acceleration shorten the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Schedule compression](https://pmdecoder.com/en/glossary/schedule-compression-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Crashing](https://pmdecoder.com/en/glossary/crashing/), [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking/)

## Distinction

Compression shortens the duration while keeping the scope the same; if scope is cut instead, this is called scope reduction. Resource levelling pursues a different aim: it removes overloads and tends to lengthen the schedule in the process. Simply moving a date is not compression either.

## In practice

A car manufacturer brings forward the start of series production of a model by six weeks. The tooling project then compresses its schedule: additional shifts are commissioned for two critical tools, and testing of the first parts begins before all tools have been finally released. The team documents that this involves extra costs and a higher risk of rework, and has both confirmed by the client.

## Frequently asked questions

### Which technique is chosen first?

The one with the best ratio of time gained to extra cost and risk. Fast tracking is often cheaper but riskier, crashing safer but more expensive.

### Does compression have limits?

Yes. Some activities can be neither accelerated nor overlapped, and beyond a certain point additional staff cause more coordination than progress.

## Related terms

- [Crashing](https://pmdecoder.com/en/glossary/crashing/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking/)
- [Schedule management](https://pmdecoder.com/en/glossary/schedule-management/)

---