# Schedule buffer

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.83
- Edition: ISO 21506:2024
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/schedule-buffer/

## Definition

A schedule buffer is a planned period with no work assigned to it, placed for example before important dates, at the end of a phase or before the end of the project. If an activity is delayed, it first eats into the buffer; the following milestone is unaffected as long as the buffer lasts. For this to work, the buffer has to be visible, and its consumption is monitored and reported regularly.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The float of an activity is calculated from the network schedule, whereas a schedule buffer is set deliberately. In critical chain project management, safety margins are taken out of individual activities and pooled in project and feeding buffers, a special form of schedule buffer. The risk contingency reserve can include time as well as money, but it is tied to specific risks.

## In practice

An automotive supplier has to achieve the production start of a new component by a fixed date. The project manager plans a three-week schedule buffer before the "Tooling approval" milestone and another two weeks before the production start. When tooling adjustments take two weeks longer, the first buffer shrinks to one week, but tooling approval stays on schedule. The report shows the buffer consumption as an early warning sign, not as a delay.

## Frequently asked questions

### Where are schedule buffers best placed?

Before dates that cannot be moved, such as contractual milestones, trade fairs or handovers to other projects, and where many paths in the network schedule converge.

### Why are buffers often used up anyway?

Because work that has more time available tends to fill that time. A buffer that is visible and monitored jointly counteracts this.

## Related terms

- [Float](https://pmdecoder.com/en/glossary/float/)
- [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
