# S-curve analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Cumulative development over the project duration](https://pmdecoder.com/en/concept/cumulative-development-over-the-project-duration/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/s-curve-analysis/

## Definition

S-curve analysis is a graphical analysis in which cumulative quantities such as cost, labour hours or the share of work completed are plotted against the project duration. Because projects usually start slowly, are most intensive in the middle and taper off towards the end, the result is typically an S-shaped curve. In the PMI context, the display is mainly used to show planned value, earned value and actual cost together. The gap between the curves and their shape reveal schedule and cost variances and trends at a glance.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [S-curve](https://pmdecoder.com/en/glossary/s-curve/) | closely related | denotes the analysis based on the curve, not the curve itself |

## Distinction

The cross-framework term S-curve refers to the curve itself; the PMI term emphasizes the analysis carried out with it and is therefore only closely related. A burndown chart shows remaining rather than cumulative work and therefore falls over time. Trend analysis can use S-curves but is not limited to this display.

## In practice

For the construction of a school, project controls show three curves in the monthly report: planned work, work performed and costs incurred. After seven months, the performance curve is clearly below the planned curve, while the cost curve is above it. Without looking at tables, the client sees that the project is both behind schedule and more expensive than planned, and asks for an action plan.

## Frequently asked questions

### Why is the curve S-shaped?

At the start, few people work on preparation and planning; in the middle, many tasks run in parallel; at the end, only closing work remains. The increase per unit of time is therefore greatest in the middle.

### What are the limits of S-curve analysis?

It shows totals and hides which work packages cause the variance. Its value also depends on how reliably progress is measured. Finding causes requires variance analysis at a lower level.

## Related terms

- [S-curve](https://pmdecoder.com/en/glossary/s-curve/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost-pmi/)
- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.