# Rolling wave planning

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.82
- Edition: ISO 21506:2024
- Concept: [Progressively refined planning](https://pmdecoder.com/en/concept/progressively-refined-planning/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/rolling-wave-planning/

## Definition

In rolling wave planning, the planning horizon is divided into stages. A detailed plan with work packages, dates and responsibilities is produced for the next few weeks or months, while later stages appear only as rough blocks or milestones. As soon as new information becomes available, usually at fixed intervals or before a new stage, the next part is refined.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Rolling wave planning](https://pmdecoder.com/en/glossary/rolling-wave-planning-pmi/) | equivalent | — |

## Distinction

Rolling wave planning is one way of elaborating plans progressively, making them more precise as knowledge grows. Unlike agile iteration planning, it usually retains an overall plan with fixed end dates. Nor does it replace an approved overall framework: the rough plan is approved and the details follow.

## In practice

A chemical park is planning to modernize its wastewater plant over three years. The first year, covering planning and permits, is planned at weekly level, while construction and commissioning appear in the plan as monthly blocks. Every quarter, the team refines the next six months. When the permit contains additional conditions, only one rough block has to be replanned rather than a construction sequence that had been worked out in detail prematurely.

## Frequently asked questions

### Which projects is rolling wave planning suitable for?

Long undertakings with high uncertainty in later stages, such as research, construction or large IT projects.

### How far ahead should the detailed horizon extend?

One to three months is typical. What matters is how far reliable information reaches.

## Related terms

- [Agile project management](https://pmdecoder.com/en/glossary/agile-project-management/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone/)
- [Decomposition](https://pmdecoder.com/en/glossary/decomposition/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.