# Rolling wave planning

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Progressively refined planning](https://pmdecoder.com/en/concept/progressively-refined-planning/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Canonical version: https://pmdecoder.com/en/glossary/rolling-wave-planning-pmi/

## Definition

In PMI usage, rolling wave planning is an iterative planning technique: work due soon is planned in detail, work further in the future initially only at a higher level. As more becomes known, the next wave is elaborated. In the work breakdown structure, later work can therefore temporarily be shown as a planning package that has a scope and a budget but no individual activities yet. The technique is a form of progressive elaboration and is particularly suitable when the results of earlier phases determine later work.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Rolling wave planning](https://pmdecoder.com/en/glossary/rolling-wave-planning/) | equivalent | — |

## Distinction

Rolling wave planning as described in ISO 21506 refers to the same thing; this entry gives the PMI view. Unlike iteration planning in agile approaches, rolling wave planning remains tied to an overall plan with baselines that is detailed step by step. A high-level schedule is a result, rolling wave planning a way of working.

## In practice

A pharmaceutical company is planning the development of a drug over several years. The current laboratory phase is planned down to individual test series, whereas the clinical trials appear in the plan only as planning packages with a budget range. Only when the laboratory results are available and the dose has been set does the team plan the first trial phase in detail, then elaborate the next wave again.

## Frequently asked questions

### How far ahead is detailed planning done?

That depends on the project. Detailed planning often covers a few weeks or months or extends to the next phase boundary. What matters is to complete the elaboration in good time before the work starts.

### Does rolling wave planning contradict a fixed baseline?

No. Parts planned at a high level also have a scope, budget and time frame and are part of the baseline. During elaboration they are converted into work packages and activities without leaving that frame.

## Related terms

- [Rolling wave planning](https://pmdecoder.com/en/glossary/rolling-wave-planning/)
- [Decomposition](https://pmdecoder.com/en/glossary/decomposition-pmi/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Control account](https://pmdecoder.com/en/glossary/control-account-pmi/)