# Risk tolerance

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.81
- Edition: ISO 21506:2024
- Concept: [Threshold at which a risk triggers action](https://pmdecoder.com/en/concept/threshold-at-which-a-risk-triggers-action/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-tolerance/

## Definition

Risk tolerance translates an organization's attitude to risk into tangible limits. It specifies, for example, how much delay, what additional costs or what probability of serious damage can still be accepted. As long as the assessment of a risk stays below this limit, monitoring is enough; once it is crossed, risk responses or escalation are mandatory. The limits are assessed, agreed and explicitly adopted by the responsible body in advance.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk threshold](https://pmdecoder.com/en/glossary/risk-threshold/) | closely related | refers to the measurable limit above which action is taken, and is defined more narrowly |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Risk appetite describes in general terms how much risk an organization is willing to take on to achieve its objectives. Risk tolerance turns this into measurable limits for a specific undertaking. A variance threshold refers to deviations from the plan that have already occurred, risk tolerance to possible future events.

## In practice

For the construction of a filling line, a pharmaceutical company decides that risks with an expected loss of more than 500,000 euros or a possible delay of more than six weeks exceed the project's risk tolerance. When it emerges that a supplier of stainless steel components is in financial difficulty and a delay of eight weeks is looming, the project manager has to present a response within one week. The response is to qualify a second supplier.

## Frequently asked questions

### Who sets risk tolerance?

The body that has to bear the consequences, usually the client, the sponsor or the steering committee, often on the project manager's proposal. Programmes and portfolios often have their own, higher-level limits.

### Can risk tolerance change during the project?

Yes. As a project approaches a fixed date, such as a trade fair or a statutory deadline, tolerance for schedule risks often drops considerably. Such adjustments should be decided explicitly.

## Related terms

- [Risk appetite](https://pmdecoder.com/en/glossary/risk-appetite/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)
- [Variance threshold](https://pmdecoder.com/en/glossary/variance-threshold/)
- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.