# Risk threshold

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Threshold at which a risk triggers action](https://pmdecoder.com/en/concept/threshold-at-which-a-risk-triggers-action/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-threshold/

## Definition

In PMI terms, the risk threshold defines the level of risk exposure at which action is required. If a risk or the overall uncertainty lies above it, responses are needed; below it, the risk may be accepted. Thresholds are expressed for individual objectives, for example as an allowable deviation from the end date or the budget, and are derived from the risk appetite of the organization and key stakeholders. They are usually recorded in the risk management plan and feed into the probability and impact matrix, whose cells show which risks lie above the threshold.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Risk tolerance](https://pmdecoder.com/en/glossary/risk-tolerance/) | closely related | refers to the measurable limit above which action is taken, and is defined more narrowly |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term is closely related to risk tolerance in ISO 21506, which likewise describes a limit on acceptable risk exposure; the naming and perspective differ. Risk appetite is the underlying stance, and the risk threshold its measurable form. A variance threshold in project control concerns deviations that have already occurred, not risks.

## In practice

For a product development project, senior management accepts no more than four weeks' delay in market entry and a five per cent budget overrun. The project manager enters these values as risk thresholds in the risk management plan. Any risk that, alone or together with others, could exceed one of these limits receives an active response.

## Frequently asked questions

### Does a risk threshold apply to the whole project or to individual risks?

Both are possible. Thresholds can apply to the whole project per objective and be broken down for rating individual risks.

### Who sets the risk threshold?

It is derived from the risk appetite of the organization and key stakeholders and agreed with the sponsor. The project manager documents it in the risk management plan.

## Related terms

- [Risk tolerance](https://pmdecoder.com/en/glossary/risk-tolerance/)
- [Risk appetite](https://pmdecoder.com/en/glossary/risk-appetite-pmi/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)
- [Probability and impact matrix](https://pmdecoder.com/en/glossary/probability-and-impact-matrix/)
- [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance-pmi/)

---