# Risk response

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Selecting and implementing risk responses](https://pmdecoder.com/en/concept/selecting-and-implementing-risk-responses/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-response-pmi/

## Definition

In PMI terms, a risk response is the reaction selected, agreed and implemented for a risk. For threats PMI identifies the strategies escalate, avoid, transfer, mitigate and accept; for opportunities, escalate, exploit, share, enhance and accept. Escalation is appropriate when a risk lies outside the project's remit. Strategies can also be chosen for the overall uncertainty of the project. Each response includes specific actions, a named owner, dates and, where needed, budget. Its effectiveness is monitored as the project continues.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Risk response](https://pmdecoder.com/en/glossary/risk-response/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk management](https://pmdecoder.com/en/glossary/risk-management-pmi/)
- Narrower terms: [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance-pmi/), [Risk avoidance](https://pmdecoder.com/en/glossary/risk-avoidance-pmi/), [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation-pmi/), [Risk transference](https://pmdecoder.com/en/glossary/risk-transference/)

## Distinction

The term corresponds to risk response in ISO 21506. It is the umbrella term for the individual strategies such as risk avoidance or risk mitigation. A contingency plan is a prepared response that only comes into effect when the risk occurs or is triggered. A workaround is not a planned risk response but an improvised fix.

## In practice

For an IT project with limited staff, the threat “loss of the only database expert” is assessed. The team chooses mitigation: a second colleague is trained and key procedures are documented. The team lead is the owner, and the deadline is the end of next month.

## Frequently asked questions

### Can several strategies be combined?

Yes. A common pattern is to mitigate a risk first and keep a contingency plan with a reserve for the remaining part.

### When is escalation the right risk response?

When the risk exceeds the project's authority or scope, for instance because it affects the whole programme or the organization. The responsible higher level then takes ownership of the risk.

## Related terms

- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)
- [Risk avoidance](https://pmdecoder.com/en/glossary/risk-avoidance-pmi/)
- [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation-pmi/)
- [Risk transference](https://pmdecoder.com/en/glossary/risk-transference/)
- [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance-pmi/)
- [Contingency plan](https://pmdecoder.com/en/glossary/contingency-plan-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.