# Risk register

also: Risk log

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Central list of project risks](https://pmdecoder.com/en/concept/central-list-of-project-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-register/

## Definition

The risk register is the working document of risk management. For each risk it contains an identifier, a description with cause and effect, the category, the assessment, the responsible person, planned and implemented responses, triggers for prepared reactions and the status. It is updated regularly during the project and evaluated at the end for future undertakings.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/) | equivalent | — |
| PRINCE2 | [Risk Register](https://pmdecoder.com/en/glossary/risk-register-prince2/) | equivalent | The PRINCE2 register explicitly includes opportunities as well. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The risk matrix shows the distribution graphically; the register contains the details. An issue log records problems that have already occurred, the risk register possible future events. A company-wide risk database collects risks from many projects and serves as a source of knowledge for new undertakings.

## In practice

The risk register of a new hospital building contains 80 entries. At every site meeting, the ten highest-rated risks are reviewed, the rest once a month. One entry reads: groundwater higher than stated in the survey report, consequence additional cost and four weeks' delay, owner the civil engineering site manager, response additional water level measurements before construction starts. After the measurements, the risk is downgraded and remains in the register as monitored.

## Frequently asked questions

### How many risks belong in the register?

All that have been identified, but not every one needs to be worked on with the same intensity. What matters is that the most important ones are discussed regularly.

### Are resolved risks deleted?

No, they are marked as closed. This keeps a traceable record of which risks existed and how they were handled.

## Related terms

- [Risk management](https://pmdecoder.com/en/glossary/risk-management/)
- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Risk category](https://pmdecoder.com/en/glossary/risk-category/)

---