# Risk register

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Central list of project risks](https://pmdecoder.com/en/concept/central-list-of-project-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-register-pmi/

## Definition

In PMI terms, the risk register is the central record of individual project risks. It holds the results of risk work: identifier and description of each risk, cause, owner, rating by probability and impact, priority, chosen response strategy, agreed actions, triggers, reserves and status. It is created during the first risk identification and kept up to date throughout the project. PMI counts it among the project documents. For an overall view of project uncertainty, PMI also provides for a risk report that summarizes the register.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Risk Register](https://pmdecoder.com/en/glossary/risk-register-prince2/) | equivalent | The PRINCE2 register explicitly includes opportunities as well. |
| cross-framework | [Risk register](https://pmdecoder.com/en/glossary/risk-register/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term corresponds to the cross-framework concept of the risk register. The issue log records problems that have occurred; the risk register records future uncertainties. The risk management plan specifies how the register is kept but does not itself contain individual risks.

## In practice

The team building a new bridge keeps the risk register as a shared spreadsheet. Each row contains a risk with owner, rating and actions. After a flood causes work to stop, the risk “water level above site dewatering capacity” is rated higher, an additional sheet pile wall is added as an action and the status is set to “in progress”.

## Frequently asked questions

### Are closed risks deleted from the risk register?

It is usual to mark them as closed rather than delete them. This keeps a record of how the project handled them and keeps the data available for lessons learned.

### Who maintains the risk register?

The project manager ensures that it is kept. The owners of individual risks provide updates to their entries.

## Related terms

- [Risk register](https://pmdecoder.com/en/glossary/risk-register/)
- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification-pmi/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)
- [Issue log](https://pmdecoder.com/en/glossary/issue-log/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)

---