# Risk

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Risk in a project](https://pmdecoder.com/en/concept/risk-in-a-project/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-pmi/

## Definition

PMI understands risk as an event or condition whose occurrence is uncertain and which, if it occurs, affects at least one project objective. The effect may be adverse or beneficial, so PMI groups threats and opportunities under a single umbrella term. A risk is usually described by its cause, the uncertain event itself and its possible consequences, and assessed by probability of occurrence and impact. PMI also distinguishes individual risks, which can be named and handled one by one, from the overall uncertainty of the project that results from all sources of uncertainty taken together.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Risk](https://pmdecoder.com/en/glossary/risk/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/), [Residual risk](https://pmdecoder.com/en/glossary/residual-risk-pmi/), [Secondary risk](https://pmdecoder.com/en/glossary/secondary-risk-pmi/), [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)

## Distinction

The term matches risk in ISO 21506, which also covers both directions of effect. In everyday usage “risk” often means only danger; in PMI terms that is a threat. A problem that has already occurred is no longer a risk but an issue. Risk differs from residual risk in that the latter is what remains after planned responses.

## In practice

When introducing new accounting software, the team records two risks: the data export from the legacy system might be incomplete (threat), and the vendor might release a migration tool earlier than announced (opportunity). Both are entered in the risk register with cause, probability, impact and a named owner.

## Frequently asked questions

### Does PMI also count positive uncertainty as risk?

Yes. An uncertainty that would benefit an objective is an opportunity and therefore also a risk. Separate response strategies apply to it, such as exploiting or enhancing it.

### How does a risk differ from an issue?

A risk lies in the future and is uncertain. An issue has already occurred or is certain and needs to be resolved. When a risk materializes, it becomes an issue.

## Related terms

- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/)
- [Risk management](https://pmdecoder.com/en/glossary/risk-management-pmi/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/)
- [Residual risk](https://pmdecoder.com/en/glossary/residual-risk-pmi/)

---