# Risk mitigation

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Reducing probability or impact](https://pmdecoder.com/en/concept/reducing-probability-or-impact/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-mitigation-pmi/

## Definition

In PMI terms, risk mitigation is a response strategy for threats. The project takes early action to reduce the probability of occurrence, the severity of the consequences, or both. The underlying idea is that preventive action is usually cheaper than repairing damage once it has occurred. Examples are additional testing, less complex solutions, prototypes, redundant components or choosing a more reliable supplier. Where an action cannot address probability, it can deliberately limit the impact. PMI's counterpart for opportunities is enhancing them.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)

## Distinction

The term corresponds to the cross-framework concept of risk mitigation. Risk avoidance seeks to eliminate the threat entirely; risk mitigation only reduces it, leaving a residual risk. Risk transference shifts the consequences to a third party instead of reducing them. A contingency plan only comes into play when the risk occurs; mitigation acts beforehand.

## In practice

In a data migration project at an insurer, there is a danger that faulty legacy data will delay go-live. The team carries out two trial migrations with complete data sets and sets up automated plausibility checks. As a result, the probability of a delay falls from high to low.

## Frequently asked questions

### How can you tell whether risk mitigation is working?

By reassessing the risk after the action has been carried out. If probability or impact falls as planned, it has worked; otherwise further steps are needed.

### Can risk mitigation cost too much?

Yes. The cost of the action should be in reasonable proportion to the expected reduction in damage. Otherwise risk acceptance may be the better choice.

## Related terms

- [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)
- [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)
- [Risk avoidance](https://pmdecoder.com/en/glossary/risk-avoidance-pmi/)
- [Residual risk](https://pmdecoder.com/en/glossary/residual-risk-pmi/)
- [Secondary risk](https://pmdecoder.com/en/glossary/secondary-risk-pmi/)

---