# Risk management

also: Project risk management

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Systematic handling of uncertainty in a project](https://pmdecoder.com/en/concept/systematic-handling-of-uncertainty-in-a-project/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-management/

## Definition

Risk management ensures that a project does not leave uncertainty to chance. It covers planning the approach, identifying possible risks, assessing them by probability and impact, selecting and implementing responses, and regularly checking whether risks have changed or new ones have emerged. A general framework for this is described in the standard ISO 31000.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk management](https://pmdecoder.com/en/glossary/risk-management-pmi/) | equivalent | — |
| PRINCE2 | [Risk practice](https://pmdecoder.com/en/glossary/risk-practice/) | closely related | Tailored to the individual project and linked to the business case, plans and tolerances. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Risk management looks at possible future events, whereas the issue log deals with problems that have already occurred. Crisis management starts when a serious event has actually happened. In many approaches, risk management also covers opportunities, that is, uncertainties with a potentially positive effect.

## In practice

A software company holds a one-hour risk workshop at the start of every customer project and maintains the results in a register. Every two weeks, the project manager and the team review the ten biggest risks. In one project, this review shows that a delayed interface on the customer's side has become considerably more likely. The prepared response, a simulated interface for testing, is put into effect immediately, and the test plan holds.

## Frequently asked questions

### How much risk management does a project need?

That depends on size, novelty and importance. Even small projects benefit from a short risk list; large ones need designated owners, methods and budgets.

### Who is responsible for risks?

The project manager is responsible for the process, and named risk owners for their risks and responses. Risks that the project cannot handle itself belong with the sponsor.

## Related terms

- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity/)

---