# Risk management plan

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Arrangements for risk management in a project](https://pmdecoder.com/en/concept/arrangements-for-risk-management-in-a-project/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-management-plan/

## Definition

The risk management plan describes the approach, not the individual risks. It specifies which methods are used, who has which role, how often risks are reviewed, which scales apply to probability and impact, from which values issues are escalated, how reserves are set up and released, and how risks are reported. It is produced in the planning phase, often based on a corporate standard, and adjusted as needed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/) | equivalent | — |
| PRINCE2 | [Risk Management Approach](https://pmdecoder.com/en/glossary/risk-management-approach/) | closely related | Same purpose; additionally translates the organization’s risk appetite into tolerances for the project board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The risk register contains the specific risks with their assessment and responses; the risk management plan contains the rules by which the register is kept. Risk management planning is the activity that produces this plan. A company-wide risk policy applies to all projects; the plan applies it to a single undertaking.

## In practice

For an infrastructure project with a budget of 80 million euros, the client requires a risk management plan. The document runs to eight pages: roles from risk owner to steering committee, an assessment matrix with five described levels, monthly risk meetings, a quarterly cost simulation and clear rules on who controls which reserve. In a later audit by the court of audit (Rechnungshof), the plan serves as evidence of an orderly approach.

## Frequently asked questions

### How extensive does a risk management plan need to be?

Appropriate to the size of the project. For small undertakings, half a page with owners, review rhythm and assessment scale is enough.

### When is the plan updated?

When the project scope, organization or risk situation changes significantly, or when the rules do not prove themselves in day-to-day work.

## Related terms

- [Risk management](https://pmdecoder.com/en/glossary/risk-management/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register/)
- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)
- [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.