# Risk management plan

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Arrangements for risk management in a project](https://pmdecoder.com/en/concept/arrangements-for-risk-management-in-a-project/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-management-plan-pmi/

## Definition

In PMI terms, the risk management plan is a component of the project management plan. It does not describe individual risks but the approach: which methods and data sources are used, who has which role, what budget and time are set aside for risk work and how often it takes place. It often also contains the risk categories or a risk breakdown structure, the risk appetite of key stakeholders, definitions of probability and impact levels, a probability and impact matrix, and requirements for reporting and tracking. Its scope and level of detail depend on the size and significance of the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan/) | equivalent | — |
| PRINCE2 | [Risk Management Approach](https://pmdecoder.com/en/glossary/risk-management-approach/) | closely related | Same purpose; additionally translates the organization’s risk appetite into tolerances for the project board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)

## Distinction

The term corresponds to the cross-framework concept of the risk management plan. The risk register documents the specific risks and responses; the risk management plan sets out the rules for working with them. A contingency plan, by contrast, is the prepared response to a single risk.

## In practice

For a project introducing a patient portal, the risk management plan specifies risk workshops at the start of each phase, a five-point scale for probability and impact, a colour-coded matrix, a risk coordinator in the project management office and a monthly report to the steering committee.

## Frequently asked questions

### When is the risk management plan created?

Early in planning, before risks are systematically recorded, because it sets the standards for that work. It is updated when significant changes occur.

### Does a small project need its own risk management plan?

It can be very brief or refer to an organizational template. What matters is that the rules for handling risks are known and agreed.

## Related terms

- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan/)
- [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)
- [Risk management](https://pmdecoder.com/en/glossary/risk-management-pmi/)
- [Risk appetite](https://pmdecoder.com/en/glossary/risk-appetite-pmi/)
- [Probability and impact matrix](https://pmdecoder.com/en/glossary/probability-and-impact-matrix/)
- [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.