# Risk Management Approach

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Risiko
- Edition: PRINCE2 7
- Concept: [Arrangements for risk management in a project](https://pmdecoder.com/en/concept/arrangements-for-risk-management-in-a-project/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-management-approach/

## Definition

The risk management approach describes how a PRINCE2 project puts the risk practice into effect. It sets out the procedure by which risks are identified, assessed and addressed, and specifies the tools used, such as scales for probability and impact or a risk matrix. It records how the organization’s risk appetite is translated into tolerances, who takes on which roles in risk management, when risks are reviewed and how they are reported. It often refers to risk policies of the organization or of a higher-level programme. The approach is created during initiation and becomes part of the project initiation documentation.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/) | closely related | Same purpose; additionally translates the organization’s risk appetite into tolerances for the project board. |
| cross-framework | [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan/) | closely related | Same purpose; additionally translates the organization’s risk appetite into tolerances for the project board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The risk management plan in general usage and the PMI risk management plan serve the same purpose. The difference lies mainly in how it is embedded in the PRINCE2 management products. The approach should not be confused with the register that contains the individual risks.

## In practice

For the construction of a data centre, the risk management approach defines a five-point scale for probability and impact. Risks with a product of 15 or more are reported to the project board immediately, all others in the regular report. A risk review with the team managers takes place once a month. The approach also refers to the group’s insurance policy.

## Frequently asked questions

### When is the risk management approach created?

During initiation, before the project is authorized for delivery. Risks noticed earlier are first recorded informally.

### How does it relate to risk appetite?

Risk appetite describes how much risk the organization is willing to take. The approach translates this into specific limits above which the project board is involved.

## Related terms

- [Risk practice](https://pmdecoder.com/en/glossary/risk-practice/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)
- [Risk appetite](https://pmdecoder.com/en/glossary/risk-appetite/)
- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)
- [Risk Register](https://pmdecoder.com/en/glossary/risk-register-prince2/)
- [Tolerance (PRINCE2)](https://pmdecoder.com/en/glossary/tolerance-prince2/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.