# Risk identification

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Identifying potential risks](https://pmdecoder.com/en/concept/identifying-potential-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-identification-pmi/

## Definition

In PMI terms, risk identification means recognizing individual risks and the sources that feed the overall uncertainty of the project, and documenting their characteristics. This includes a clear description in terms of cause, event and effect and, where possible, a named owner. Common means are workshops, interviews, checklists, analysis of assumptions and constraints, SWOT analysis, lessons from earlier projects and the risk breakdown structure as a search framework. The result is recorded in the risk register. Identification is not a one-off activity; it is repeated throughout the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Risk identification](https://pmdecoder.com/en/glossary/risk-identification/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk management](https://pmdecoder.com/en/glossary/risk-management-pmi/)

## Distinction

The term corresponds to the cross-framework concept of risk identification. It precedes risk analysis, which evaluates and prioritizes identified risks. Collecting problems that have already occurred is not part of it; these are kept as issues in the issue log.

## In practice

At the start of a project for a new production line, the project manager invites experts from engineering, procurement, occupational safety and operations to a half-day workshop. Using the risk breakdown structure and the lessons learned from a similar project, the group collects 35 risks, phrases each one as cause, event and effect, and names an owner for each.

## Frequently asked questions

### Who takes part in risk identification?

As many people as possible who know the undertaking from different angles: the team, subject matter experts, stakeholders and, where relevant, suppliers. Different perspectives uncover more risks.

### Why phrase risks as cause, event and effect?

It separates the fact from which a risk arises from the uncertain event and its consequences. This makes assessment easier and shows where responses can take effect.

## Related terms

- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/)
- [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/)
- [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis-pmi/)
- [SWOT analysis](https://pmdecoder.com/en/glossary/swot-analysis/)
- [Brainstorming](https://pmdecoder.com/en/glossary/brainstorming/)

---