# Risk category

also: Risk type

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Group of similar risks](https://pmdecoder.com/en/concept/group-of-similar-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-category/

## Definition

Risk categories group risks by origin or nature. Common categories are technology, requirements, organization and staff, suppliers and contracts, finance, legal and permits, and environment and market. They serve as a search grid during risk identification, make it easier to assign owners and show during evaluation where risks accumulate.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk category](https://pmdecoder.com/en/glossary/risk-category-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The category describes where a risk comes from; the assessment describes how significant it is. A risk breakdown structure arranges categories hierarchically over several levels. Categories should suit the project: software development needs different groups from a construction project.

## In practice

A consultancy evaluates the risk registers of fifty completed projects. Sorted by category, the analysis shows that more than half of the risks that materialized came from the category of customer involvement, such as late approvals or missing contact persons. The company therefore adds firm customer obligations to its standard contracts and checks them separately at the start of every project.

## Frequently asked questions

### How many categories make sense?

Usually five to ten at the top level. Too many lead to disputes over assignment; too few lose explanatory power.

### Can a risk belong to several categories?

In principle yes, but a main category helps with evaluation. Further characteristics can be recorded as tags.

## Related terms

- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register/)
- [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure/)
- [Risk management](https://pmdecoder.com/en/glossary/risk-management/)

---